Drawing changes are not scary, what's scary is verbal modifications. ECN closed loop can push the project schedule out of control to over 30%.
1、 Changes must be documented in writing
All structural modifications of the aluminum alloy casting mold project should be executed after confirmation in the ECN document.
Orders that require rework due to verbal changes have an average extension of 12 to 18 days in the project timeline.
The ECN document should include four items: change points, impact on processes, cost and schedule adjustments.
2、 Freeze the basic drawing version
Freeze the 3D drawing version number before mold opening, and increment the version number for subsequent modifications.
For projects without version management, the proportion of inconsistencies between processing and drawings can reach 15%.
The cost of modifying the mold after the cavity has been thickened is approximately 20% to 35% of the original quotation.
3、 Change grading response
Divide the changes into three levels: exterior level, cavity level, and structural level, corresponding to different approvals and project timelines.
Shape level changes are usually completed within 3 days, cavity level changes take 7 to 10 days, and structural level changes may require re opening of inserts.
Graded response can avoid small changes going through the big process and prevent big changes from being underestimated.
4、 Synchronization confirmation of cost and schedule
Each ECN should synchronize the confirmation of fees and delivery dates to avoid disputes arising from centralized reconciliation at the end of the month.
Industry data shows that the dispute rate for final payments of synchronously confirmed projects is about 40% lower.
Xinfeng attached an impact assessment form with ECN in the customized project for internal approval by the client.
5、 Integrate with internal customer processes
Overseas customer changes often require both internal engineering and procurement signatures, with a lead time of approximately 5 to 7 days.
Suppliers should reserve a buffer period to avoid delays in customer approval and squeezing production schedules.
The contract may stipulate a time limit for approval of changes, and if the deadline is exceeded, the delivery date will be automatically extended.
Conclusion and Outlook
ECN is not an administrative process, but a controller of schedule and cost.
Implement version freeze, graded response, and cost synchronization to reduce rework and disputes simultaneously.
Extension: Three Quantitative Nodes of Change Management
After precision machining of the mold cavity, the rework cost is about 2.5 times that of the rough machining stage.
The change concentration occurs after the trial mold, accounting for 60% of all changes.
Each change has an average impact on the construction period of 5 to 9 days, and a buffer should be reserved in the scheduling.
Setting up reviews according to nodes can keep the cost of changes within a controllable range.
Xinfeng provides a change cost comparison table by node in the customized project.
After node pre positioning, the probability of overall project delay usually decreases by about 30%.
Addendum: Three Connections in the Change Process
Change requests should be initiated by the customer's engineering department, and verbal communication from sales is often mistaken for informal requirements.
The changes made after rough cutting need to be evaluated whether the inlay can be retained, which can save about 30% of the mold modification cost.
After each change, update the drawing list and version comparison table to prevent the misuse of old drawings during the assembly phase.
Addendum 2: Two indicators for change evaluation
Re calculate the lifespan of the mold after the change, and the lifespan may decrease by about 15% when there are significant structural modifications.
The increase in testing items caused by changes requires synchronous verification of testing hours and costs.
FAQ
Do drawings need to be changed in writing? Must be confirmed by ECN before execution.
How long will the verbal change be delayed? The average construction period is extended by 12 to 18 days.
How much does it cost to change the mold after rough opening? Approximately 20% to 35% of the original quotation.
How many levels of changes are there? There are three levels: exterior level, cavity level, and structural level.
How long will the appearance level change take to complete? Usually within 3 days.
How long does it usually take for customer approval? About 5 to 7 days, buffer needs to be reserved.
How to reduce final payment disputes? Confirm the cost and delivery date synchronously for each change.
How to schedule the delivery cycle of aluminum alloy casting molds: 35 days
Moldes para fundição por baixa pressão (LPDC)
Moldes para fundição por gravidade
Moldes para fundição por contrapressão (CPC)
Moldes para fundição de peças estruturais
Molde para fundição de cubos de roda de motocicleta
Molde para fundição por pressão diferencial de cubos de roda
Molde para fundição por gravidade de cubos de roda
Molde para fundição por baixa pressão de cubos de roda
MOLDES PARA JANTES AUTOMÓVEIS
PEÇAS ESTRUTURAIS AUTOMÓVEIS
OUTROS COMPONENTES DE FUNDIDOS DE ALUMÍNIO
PERFIL DA EMPRESA
ESTRUTURA ORGANIZACIONAL
HISTÓRICO DE DESENVOLVIMENTO
PROPRIEDADE INTELECTUAL
ESPÍRITO DE EQUIPA PARCEIRO
Copyright © Zhejiang Xinfeng Machinery Co., Ltd. All Rights Reserved.