The three key provisions of the mold contract are: free trial mold times, acceptance standards, and overdue billing method.

  • Vistas: ...
  • Tempo de liberação: 2026-11-16

The three key provisions of the mold contract are: free trial mold times, acceptance standards, and overdue billing method.

1、 Free trial times

It is customary in the industry to offer two free mold trials, and any excess will be charged at approximately 3% of the mold fee per trial.

Unspecified contracts, trial mold disputes account for more than 60% of final payment disputes.

The definition of trial molding should specify whether it includes clamping, debugging, and testing to avoid inconsistent diameters.

2、 The acceptance criteria should be quantifiable

The acceptance criteria usually include four items: full-size, porosity, surface defects, and beat rate.

It is recommended to write 2% for porosity release line and 1.2% for safety components, and indicate the testing method.

It is not uncommon for customers and suppliers to have opposite judgments on the same item when the standards are vague.

3、 Excessive billing and responsibility allocation

The supplier shall bear the cost of trial mold failure caused by mold design reasons.

Repeated trial molds caused by customer changes in drawings will be charged on a per use basis and the construction period will be extended accordingly.

ECN changes require written confirmation, and disputes arising from verbal modifications account for over 60%.

4、 Delivery and final payment milestones

The common milestones are 30% payment for drawing confirmation, 40% payment for trial mold qualification, and 30% payment for mass production acceptance.

The final payment conditions should specify the specific documents of acceptance completion, such as the three coordinate report and trial mold record.

Xinfeng specifies the template for trial mold records in the contract to reduce discrepancies in acceptance criteria.

5、 Risk Warning

Exchange rates and shipping costs fluctuate, it is recommended to agree on an adjustment mechanism beyond the 3% threshold.

The ownership of molds and the intellectual property rights of drawings need to be listed separately to avoid subsequent disputes.

Industry practice has shown that contracts with clear terms shorten the average recovery period for final payments by about 20 days.

Conclusion and Outlook

Disputes over mold contracts often arise from vague expressions rather than the price itself.

Writing quantifiable terms for frequency, standard, and responsibility significantly reduces the cost of performance.

Extension: Three easily overlooked sentences in a contract

The acceptance shall be based on the samples confirmed by both parties. Failure to seal the samples will affect subsequent judgments.

The construction period has been postponed due to customer reasons, without specifying the number of days for postponement. The actual dispute duration can reach several weeks.

The ownership of the mold will be transferred upon full payment of the final installment, and any missing information may result in disputes over resolution.

Three sentences may seem like details in a contract, but they actually affect the cost and risk of performance.

Industry practice shows that projects with complete terms require an average of two fewer lawyer communications.

Write the key sentence in the attachment and have both parties sign it, significantly reducing disputes during the execution phase.

Addendum: Three requirements for leaving marks during the trial molding process

The trial model record should include equipment parameters. Inconsistent parameters during machine replacement and reproduction can lead to invalid conclusions.

It is recommended to keep at least 3 test samples for future comparison and customer confirmation.

The cost terms for extra trial molds need to be confirmed before mold opening, and negotiations afterwards are usually passive.

Addendum 2: Two Agreements on Acceptance Nodes

The acceptance should be completed within 7 days after the mold arrives at the factory. If the deadline is exceeded, it will be considered as a default pass and prior agreement is required.

The ownership of spare parts and samples should be clearly stated to avoid delivery delays caused by customer requests for retention of parts.

FAQ

How many free trial runs is reasonable? Normally, if exceeded twice, it will be calculated at approximately 3% of the mold cost.

Does the trial mold include debugging? It should be clearly stated in the contract to avoid inconsistencies in wording.

What are the acceptance criteria? Full size, porosity, surface defects, and beat rate.

What is the porosity release line? Universal 2%, safety components 1.2%.

Who will pay for the customer's image modification? Pay per use and extend the construction period accordingly.

How to set up payment nodes? Commonly seen at 30%, 40%, and 30%.

How to shorten the final payment cycle? Export orders can usually be shortened by about 20 days.
Aluminum alloy casting mold drawing change: how to avoid schedule loss in ECN process

Sítio Web Deste artigo: https://pt.zj-xinfeng.com/case/1485.html

Get a Custom Product Proposal Online

Please fill out the form below to receive this for free.

Global Hotline:

+86-15356852630,13967513266

Moldes para fundição por baixa pressão (LPDC) 
Moldes para fundição por gravidade 
Moldes para fundição por contrapressão (CPC) 
Moldes para fundição de peças estruturais
Molde para fundição de cubos de roda de motocicleta
Molde para fundição por pressão diferencial de cubos de roda
Molde para fundição por gravidade de cubos de roda
Molde para fundição por baixa pressão de cubos de roda

MOLDES PARA JANTES AUTOMÓVEIS 
PEÇAS ESTRUTURAIS AUTOMÓVEIS 
OUTROS COMPONENTES DE FUNDIDOS DE ALUMÍNIO

NOTÍCIAS DA EMPRESA
NOTÍCIAS DO SETOR
BLOG TÉCNICO
PERGUNTAS FREQUENTES

PERFIL DA EMPRESA
ESTRUTURA ORGANIZACIONAL
HISTÓRICO DE DESENVOLVIMENTO
PROPRIEDADE INTELECTUAL
ESPÍRITO DE EQUIPA PARCEIRO

Copyright © Zhejiang Xinfeng Machinery Co., Ltd. All Rights Reserved.