Perguntas frequentes

The key to 35 day delivery is parallel scheduling, with four overlapping stages of design, material preparation, rough machining, and precision machining.

  • Vistas: ...
  • Tempo de liberação: 2026-11-16

The key to 35 day delivery is parallel scheduling, with four overlapping stages of design, material preparation, rough machining, and precision machining.

1、 Cycle benchmark and disassembly

The regular delivery cycle for aluminum alloy casting molds is 30 to 40 days, with gravity molds taking about 30 days and CPC molds taking about 40 days.

The dismantling cycle is divided into 5 days for design, 7 days for material preparation, 8 days for rough machining, 10 days for precision machining, and 7 days for assembly and trial molding.

Parallel scheduling can compress the total cycle by about 20%, while serial scheduling often exceeds 45 days.

2、 Parallel design and material preparation

Simultaneously initiating the drawing review and placing the steel order can save 3 to 5 days of waiting.

The delay in the arrival of steel is one of the main reasons for the delay, accounting for about 30%.

Maintaining safety stock for commonly used steel grades can shorten the preparation time to within 5 days.

3、 Connection of processing procedures

Rough machining and precision machining are sorted according to the priority of the cavity, with long cycle deep cavities being done first.

The precision machining of a single set of cavities on a five axis machining center usually takes 6 to 10 days.

Night shift and dual machine parallel connection can shorten processing time by about 30%, but it requires matching detection resources.

4、 Trial molding and rectification

The first trial is usually scheduled for 2 days, followed by 3 to 5 days for rectification, and 2 days for the second trial.

The trial mold scheduling needs to be aligned with the customer's press schedule, with an average delay of 4 days for incorrect scheduling.

Xinfeng locks the trial mold window at the start of the project to reduce waiting time.

5、 Overlay of foreign trade logistics

Shipping to Europe takes about 30 to 35 days, and to Southeast Asia takes about 10 to 15 days, which needs to be aligned with the customer's production schedule.

Export customs declaration and wooden box packaging usually take 3 days, which is not included in the production cycle.

Industry practice shows that parallel scheduling projects can increase on-time delivery rates by about 25%.

Conclusion and Outlook

Delivery time is a reflection of scheduling ability, not a result of price pressure.

Design parallel material preparation, prioritize processing, and lock the trial mold window, which can be stably achieved within 35 days.

Extension: Three pitfalls that are easy to fall into when compressing delivery time

The compression processing time will widen the cavity tolerance from 0.02 millimeters to 0.04 millimeters.

Omitting the mold closing inspection often takes an additional 3 to 5 days for rework during mold testing.

The trial window is not locked, and waiting time may swallow all the compressed results.

When the three items are combined, the delivery time appears to be shortened, but the actual repair rate increases by about 20%.

Compressing according to the process rather than the total amount makes the risk more controllable.

Clearly state the compression points in the project plan, and the customer's expectations will also be clearer.

Addendum: Four mechanisms for delivery management

The project kickoff meeting will clarify the five milestones and responsible persons, and only when there is a delay can specific links be traced back.

Reserve 10% buffer time for critical processes to handle equipment failures and repairs.

Update the schedule weekly and synchronize with customers, and coordinate in advance only for temporary order insertion.

Steel arrival requires size and flaw detection sampling, and about 3% of cases are found to have problems during sampling.

Addendum 2: Two Risks in Scheduling

On average, each equipment failure affects 2 to 3 days, and dual machine backup can reduce the impact by about half.

Outsourcing heat treatment often requires an additional 7 days, and not being included in the schedule will directly cause delays.

FAQ

How many days is the regular delivery time? 30 to 40 days, gravity takes about 30 days, CPC takes about 40 days.

How to dismantle the cycle? Design takes 5 days, material preparation takes 7 days, rough processing takes 8 days, and precision processing takes 10 days.

How much can parallel scheduling save? The total cycle is compressed by about 20%.

What are the main reasons for the delay? The delayed arrival of steel accounts for about 30%.

How many days does it take to test the model? First 2 days, rectification takes 3 to 5 days.

How long does it take to ship to Europe by sea? About 30 to 35 days.

How to improve the on-time performance? Parallel scheduling can increase by about 25%.

Sítio Web Deste artigo: https://pt.zj-xinfeng.com/case/1487.html

Get a Custom Product Proposal Online

Please fill out the form below to receive this for free.

Global Hotline:

+86-15356852630,13967513266

Moldes para fundição por baixa pressão (LPDC) 
Moldes para fundição por gravidade 
Moldes para fundição por contrapressão (CPC) 
Moldes para fundição de peças estruturais
Molde para fundição de cubos de roda de motocicleta
Molde para fundição por pressão diferencial de cubos de roda
Molde para fundição por gravidade de cubos de roda
Molde para fundição por baixa pressão de cubos de roda

MOLDES PARA JANTES AUTOMÓVEIS 
PEÇAS ESTRUTURAIS AUTOMÓVEIS 
OUTROS COMPONENTES DE FUNDIDOS DE ALUMÍNIO

NOTÍCIAS DA EMPRESA
NOTÍCIAS DO SETOR
BLOG TÉCNICO
PERGUNTAS FREQUENTES

PERFIL DA EMPRESA
ESTRUTURA ORGANIZACIONAL
HISTÓRICO DE DESENVOLVIMENTO
PROPRIEDADE INTELECTUAL
ESPÍRITO DE EQUIPA PARCEIRO

Copyright © Zhejiang Xinfeng Machinery Co., Ltd. All Rights Reserved.